Installation
Operation
Service Manual
for
Forced Draft Steam
Boilers
BRYAN BOILERS
783 N. CHILI AVENUE, PERU, INDIANA 46970
Telephone: 765-473-6651 / Fax: 765-473-3074
Download from Www.Somanuals.com. All Manuals Search And Download.
MINIMUM CLEARANCES
NOTE: These boilers are intended to be installed in a room which is large compared to the size of
the boiler. They are not intended for alcove installation and are suitable for installation on non-
combustible flooring only.
D-SERIES
F-SERIES1
CL-SERIES
K-SERIES
RV, RW & AB SERIES
DIMENSION
WATER/
STEAM
OVER
50#
WATER
STEAM
OVER
50#
WATER
STEAM
OVER
50#
WATER
STEAM
OVER
50#
WATER
/STEAM
TO 50#
STEAM
OVER
50#
STEAM
TO 50#
/STEAM
TO 50#
/STEAM
TO 50#
/STEAM
TO 50#
A
B
18"
24"
18"
48"
24"
36"
24"
36"
96"
24"
18"
48"
18"
18"
18"
48"
96"
36"
36"
36"
24"
48"
24"
24"
24"
24"
36"
24"
24"
24"
18"
48"
24"
24"
24"
36"
24"
24"
24"
24"
24"
48"
24"
24"
32"
24"
48"
24"
24"
32"
CV & CH
D
EL & ER
1 - F-Series boilers are approved for installation on combustible flooring. Do not install on carpeting.
A - Clearance above boiler
B - Front of boiler
CV - Clearance from gas vent, measured vertically above pipe
CH - Clearance from gas vent, measured horizontally or below pipe
D - From back of boiler
EL - Left side of boiler
ER - Right side of boiler
These clearances are general minimum clearances. Local codes may dictate larger clearances.
Download from Www.Somanuals.com. All Manuals Search And Download.
1.4 BOILER CONNECTIONS
1.4.1 GENERAL
tank. This valve can then be adjusted to
bypass excess pump capacity to better
control the boiler feed rate.
Do not run any pipes along the access panel
side of the boiler. Maintain clearances as
shown on the dimensional drawing for
servicing of the boiler tubes. Provide at least
36" from the gas train and burner, unless a
larger dimension is indicated on the
dimensional. All piping should be designed
and installed to avoid any loadings on the
boiler connections or piping.
1.4.4 SAFETY RELIEF VALVE(S)
A connection is provided in the top of the
boiler for the relief valve. The relief valve
discharge piping must be the same size as
the relief valve discharge opening. Avoid
over-tightening as this can distort valve seats.
All piping from relief valve must be
independently supported with no weight
carried by the valve.
1.4.2 STEAM SUPPLY CONNECTION
A steam shut-off valve must be installed
between each boiler and the steam main.
This valve must be of the outside screw and
yoke design to allow indication from a
distance whether the valve is open or closed.
1.4.4 BLOWDOWN CONNECTION
Blowdown valve(s) must be full size of the
connection on the boiler. Steam boilers 15
psig and below require at least one blowdown
valve. Higher pressure boilers require two
blowdown valves with one or both valves
being slow opening type. Each water column
and float type low water cut-off must be
equipped with a blowdown valve.
1.4.3 FEEDWATER CONNECTION
Install a check valve and a globe valve
between the feed pump and the boiler. It is
also recommended to install a globe valve
between the feed pump and the receiver
Download from Www.Somanuals.com. All Manuals Search And Download.
1.5 GAS SUPPLY CONNECTION - FORCED DRAFT UNITS
The installation must conform completely to the
requirements of the authority having jurisdiction,
or in the absence of such, requirements shall
conform in the U.S. to the current National Fuel
Gas Code, ANSI Z223.1-1984, or in Canada to
the current Installation Code for Gas Burning
Appliances and Equipment (CAN/CGA B149.1-
M91), or Oil Burning Equipment (CSA B139-
M91), and applicable regional regulations for the
class; which should be followed carefully in all
cases.
Drip leg must be installed on gas supply piping.
Consult the local gas utility company for
inspection and authorization of all gas supply
piping and flue connections.
The regulator vent line must be vented to outside
of building on any boiler equipment with electric
gas pilot ignition.
1.5.1 DRIP LEG
1.5.3 VENTING OF GAS TRAIN COMPONENTS
Gas pressure regulator - The regulator must be
vented to the outside air, using minimum 1/4"
tubing or pipe. The vent line should terminate in a
downward direction to be free of restriction.
A drip leg or sediment trap must be installed in
the gas supply line. See Fig. 1.5A. The gas line
must be connected to a supply main at least as
large as the gas train connection at the boiler.
This connection should be made with a union so
that the boiler gas train components and burner
may be easily removed, if necessary, for service.
Diaphragm gas valves (V48A or V88A) - The vent
line off of these gas valves must be vented to
outdoors, the same as the regulator.
1.5.2 GAS PIPING LEAK TEST
After completion of the gas piping hookup, the
installation must be checked for leaks, using a
soap and water solution. Disconnect the boiler
and gas train from the gas supply piping during
any pressure testing of the gas supply system.
Normally open vent valves - These valves must
be piped to outdoors using pipe no smaller than
that of the valve.
Gas pressure switches - Vent these switches to
outdoors using a minimum of 1/4" tubing or
piping.
FIGURE 1.5A: GAS BURNER CONNECTION
NOTE: USE PIPE COMPOUND, WHICH IS RESISTANT TO THE ACTION OF LIQUID PETROLEUM
GAS. DO NOT USE TEFLON TAPE.
Download from Www.Somanuals.com. All Manuals Search And Download.
1.6 ELECTRICAL CONNECTION
IMPORTANT: All electrical connections must
conform to the National Electrical Code and to all
other applicable State and Local Codes. Forced
details.
Equipment Grounding - The boiler must be
grounded in accordance with the American
National Standard Electrical Code, ANSI/NFPA
#70-1981.
draft boilers may require
a
high voltage
connection. See boiler wiring diagram and
equipment list for
1.7 COMBUSTION AIR SUPPLY
IMPORTANT: Positive means for supplying an
ample amount of outside air, allowing complete
combustion of the gas, must be provided.
boiler is not equipped with a draft control device
(so no air is required for draft control).
COMBUSTION AIR OPENINGS
REQUIRED:
-
AREA
Movable combustion air dampers, automatic or
manually adjustable, must be electrically
interlocked with the boiler to prevent boiler
operation if the dampers are closed.
Openings directly through outside wall -
One opening within 12 inches of the ceiling plus
one opening within 12 inches of the floor. Each
opening must have a minimum free area of 1
square inch per 4,000 Btu of total input of all air
using appliances in the room.
Combustion air openings must never be blocked
or obstructed in any manner.
The boiler room must be at a positive or neutral
pressure relative to the outdoors. A negative in
the boiler room will result in downdraft problems
and incomplete combustion due to lack of air.
Example: A boiler room having two boilers with
500,000 Btu input would require two openings
through an outside wall, and each opening must
have at least 250 square inches of free area.
Openings through vertical ducts -
One duct in the ceiling plus one duct terminating
within 12 inches of the floor. Each opening must
have a minimum free area of 1 square inch per
4,000 Btu of total input of all air-using appliances
in the room.
Example: A boiler room having four boilers with
250,000 Btu input would require two ducts, one in
the ceiling and one terminating near the floor,
each opening having at least 250 square inches
of free area.
WARNING!
Failure to provide an adequate air supply will
result in boiler damage and hazardous conditions
in the building (fire and asphyxiation hazard as
well as equipment damage).
COMBUSTION AIR: Complete combustion of
natural or propane gas requires approximately
ten cubic foot of air (at sea level and 70 F) for
each 1000 Btu of boiler input. In reality, additional
air is required to achieve complete combustion.
Air is also required for the proper operation of the
appliance draft diverter or barometric damper.
The combustion air opening recommendations
below are designed to provide the air needed for
atmospheric gas fired boilers which are equipped
with either draft diverters or barometric dampers.
Combustion air openings for boilers which are
equipped with forced draft burners may be
reduced to 70% of that required for atmospheric
gas fired boilers. This is because the forced draft
Openings through horizontal ducts -
One duct opening within 12 inches of the ceiling
plus one duct opening within 12 inches of the
floor. Each opening must have a minimum free
area of 1 square inch of per 2,000 Btu of total
input for all equipment in the room. NOTE: No
rectangular duct may have a dimension of less
than 4 inches.
Example: A boiler room having 1 million Btu total
input would require two ducts, one in the ceiling
and one near the floor, each opening must having
at least 500 square inches of free area.
Download from Www.Somanuals.com. All Manuals Search And Download.
Ventilation Air: In addition to air needed for
combustion, sufficient air must be supplied for
ventilation, including air required for comfort and
proper working conditions for personnel in the
boiler room. In colder climates, provision should
also be made to heat the boiler room, if
necessary, for personnel comfort.
disposal. The boiler room and the combustion air
supply must not be exposed to the fumes. Such
fumes include, but are not limited to, carbon
monoxide, hydrogen sulfide, ammonia, chlorine,
and halogenated hydrocarbons.
NOTE:
Halogenated
hydrocarbons
are
particularly injurious and corrosive after exposure
to high temperatures.
CAUTION
Protection from combustion air contamination:
Where corrosive or flammable process fumes are
present in the vicinity of the boiler room or the air
stream for the combustion air supply, it is
essential that suitable means be provided for their
safe
1.8 CHIMNEY, FLUE PIPE & DRAFT CONTROL - FORCED DRAFT BOILERS
CODE COMPLIANCE
ESTIMATING FLUE GAS FLOW RATE (ACFM)
Flue gas volumetric flow rate in SCFM (standard
cubic feet per minute) and ACFM (actual cubic
feet per minute) can be estimated by using the
information in 1.8.1A. Divide the Total Input of
appliances connected to the chimney or vent by
1000. Then multiply this result times the factor
listed in the SCFM and ACFM table. The ACFM
data is required for determining stack exit velocity
and induced draft fan requirements.
The installation must conform to the requirements
of NFPA 54, the National Gas Code (ANSI
Z223.1-1984), Part 7, "Venting of Equipment", or
to the applicable requirements of all local building
codes. For factory-built and listed chimney
systems (such as type B vent), consult the
system manufacturer's instructions for correct
installation procedures. Gas vents may be of any
of the construction types listed in this manual. No
portion of a venting system may extend into or
pass through any circulating air duct or plenum.
ESTIMATING STACK EXIT VELOCITY
First, determine the ACFM for the stack as
described above. Multiply the total ACFM times
the Velocity Factor from the Velocity Table in
Table 1.8.1B for the stack diameter used. The
result is the Stack Exit Velocity in feet per second.
MINIMUM SAFE PERFORMANCE
Venting systems must be designed to develop
positive flow adequate to remove flue gases to
the outside atmosphere. Guidelines are provided
in this manual and in the National Fuel Gas Code,
NFPA 54, for sizing and design of flue gas
venting systems. For additional reference to good
practice in vent design, refer to the "Chimney,
Gas Vent, and Fireplace Design" chapter of the
ASHRAE Equipment Handbook.
ESTIMATING STACK EMISSIONS
Table 1.8.1C lists approximate emissions of NOx
(oxides of nitrogen) and CO (carbon monoxide).
The table lists both the concentration, in parts per
million (ppm), and the flow rate, in pounds per
hour (PPH), of each compound: Divide the total
input of appliances connected to the chimney or
vent by 1,000,000. Then multiply this result times
the value listed in the table for PPH emissions.
OUTSIDE VENTS AND CHIMNEYS
Outside uninsulated single wall pipe is not
recommended for use in cold climates for venting
gas-fired
appliances
since
temperature
differentials may cause corrosion in such pipe, as
well as poor draft on start ups. When local
experience indicates that condensate may be a
problem, provisions should be made to drain off
the condensate in the gas vent or chimney.
MANUAL REFERENCES
See Figure 1.8.1 for a graphics listing of
applicable sections of this manual for each
section of the vent system.
Download from Www.Somanuals.com. All Manuals Search And Download.
FIG. 1.8.1: VENT DESIGN INSTRUCTION -
REFERENCES
TABLE 1.8.1A: ESTIMATING FLUE GAS VOLUMETRIC FLOW RATE
Approximate Flue Gas VOLUMETRIC FLOW RATE
(Per 1000 Btu/hr Input)
(Multiply factor listed times boiler input in MBH)
SCFM Per
1000 Btu/hr
INPUT
ACFM Per
1000 Btu/hr
INPUT
APPROXIMATE
FLUE GAS
BOILER TYPE
TEMPERATURE
Water & 15# Steam
Gas Fired
0.230
0.230
0.402
0.402
450 F
450 F
Oil Fired
150# Steam
Gas Fired
0.230
0.230
0.425
0.425
500 F
500 F
Oil Fired
TABLE 1.8.1B: STACK EXIT VELOCITY
Estimated STACK EXIT VELOCITY Calculation
(Multiply total ACFM times the velocity factor below velocity in feet per second)
STACK INSIDE
VELOCITY
FACTOR
STACK INSIDE
VELOCITY
FACTOR
STACK INSIDE
VELOCITY
FACTOR
DIAMETER (Inches)
DIAMETER (Inches)
DIAMETER (Inches)
6
7
0.0849
0.0624
0.0477
0.0306
0.0212
0.0156
0.0119
18
20
22
24
26
28
32
0.00943
0.00764
0.00631
0.00531
0.00390
0.00340
0.00298
34
36
38
40
48
60
0.00264
0.00236
0.00212
0.00191
0.00133
0.00085
8
10
12
14
16
Download from Www.Somanuals.com. All Manuals Search And Download.
TABLE 1.8.1C: ESTIMATING FLUE GAS EMISSIONS
Estimated Emissions (Volumetric Flow Rate Per Million Btu/hr Input)
(Multiply PPH listed times boiler input divided by 1,000,000)
BOILER
TYPE
PARTICULATES
NOx
CO
SOx
Hydrocarbons
PPH per
MMBH
PPM
PPH per
PPM
PPH per
MMBH
PPM
PPH per
PPM
PPH per
PPM
MMBH
MMBH
MMBH
Gas Fired
Oil Fired
N/A
N/A
20
0.049
50
70
0.194
0.018
200
18
N/A
N/A
290
0.010
10
4
0.020
0.068
0.286
0.004
1.8.2 CLEARANCES
The vent system and draft control devices must
be installed so as to achieve the clearances to
surfaces outlined in Table 1.2.1, Minimum
Clearances chart, in this manual. See also Table
1.8.9 for vent clearances. All clearances must
comply with the National Fuel Gas Code
(NFPA54), and with all
local and state building codes. The clearances
described in this manual are intended to be
general guidelines only, additional requirements
may occur because of local building design
regulations.
1.8.3 BOILER ROOM PRESSURIZATION
The boiler room must be supplied with adequate
air for combustion and for proper operation of
draft control devices (barometric dampers or draft
diverters) as outlined in "Combustion Air Supply",
Section 1.7 of this manual.
WARNING
THE BOILER ROOM MUST BE MAINTAINED
AT A POSITIVE OR NEUTRAL PRESSURE
(RELATIVE TO OUTDOORS) AT ALL TIMES.
EXHAUST FANS OR CONNECTIONS FROM
THE BOILER ROOM TO ZONES OF NEGATIVE
INDUCED DRAFT FAN WILL BE REQUIRED.
FURTHER, THE BOILER MUST BE PROVIDED
WITH A BAROMETRIC DRAFT CONTROL -
NOT WITH A DRAFT DIVERTER. THE FAN
MUST BE INTERLOCKED WITH THE BOILER
AND A DRAFT PROVING SWITCH MUST BE
INSTALLED TO PREVENT OPERATION OF
THE BOILER IF THE FAN SHOULD FAIL TO
OPERATE.
PRESSURE
(AIR
DUCTS,
NEGATIVE
PRESSURE ROOMS, ETC.) WILL CAUSE
NEGATIVE PRESSURE IN THE BOILER
ROOM. SUCH CONDITIONS WILL CAUSE
HAZARDOUS OPERATION OF THE BOILER
AND INTRODUCTION OF COMBUSTION
PRODUCTS INTO THE BUILDING AIR.
IT ALSO MAY BE ADVISABLE TO INSTALL AN
AUTOMATIC VENT DAMPER IN THE VENT
SYSTEM
TO
PREVENT
BACKFLOW
IF THE BOILER ROOM MUST BE UNDER A
NEGATIVE PRESSURE AT ANY TIME, AN
THROUGH THE VENT SYSTEM DURING
BOILER OFF CYCLES. SEE FOLLOWING
SECTION ON AUTOMATIC VENT DAMPERS.
Download from Www.Somanuals.com. All Manuals Search And Download.
1.8.7 ACCEPTABLE VENT TYPES
LISTED GAS VENTS
installed in accordance with nationally recognized
building codes or standards.
Listed gas vents must be applied only on those
applications for which they are listed. Type B gas
vents are NOT listed for use on forced draft
appliance vent systems.
MASONRY CHIMNEYS FOR RESIDENTIAL
APPLICATIONS MUST BE LINED WITH FIRE-
CLAY FLUE LINING (KX C315 OR THE
EQUIVALENT) WITH THICKNESS NOT LESS
THAN 5/16 INCH OR WITH A LINER OF OTHER
APPROVED MATERIAL THAT WILL RESIST
CORROSION, SOFTENING OR CRACKING
FROM FLUE GASES AT TEMPERATURES UP
TO 1800 F.
Installation of these vents must comply with the
vent listing, with the vent manufacturer's
instructions and with complete adherence to the
codes and clearances as outlined previously.
PRESSURIZED VENT SYSTEMS
Some Bryan Boilers (unless specifically fitted for
the application) are not suitable for operation on a
pressurized vent systems. Refer to Section 2 of
this manual for the allowable range of vent
pressure for each series. The RV, RW, and AB
series boilers are designed for pressurized vent
systems. All others require a neutral pressure.
EXISTING
CHIMNEYS
SHOULD
BE
INSPECTED FOR UNSAFE CONDITIONS,
SUCH AS DETERIORATED MASONRY AND
EXCESSIVE SOOT OR OTHER BLOCKAGE OR
POTENTIAL BLOCKAGE. SEE ALSO SECTION
1.8.6.
EXISTING CHIMNEYS MUST BE PROPERLY
SIZED FOR THE FLUE GAS LOADING TO BE
USED. THAT IS, IF AN EXISTING CHIMNEY IS
USED FOR A SMALLER TOTAL INPUT THAN
ITS ORIGINAL DESIGN, A LINER OR VENT IS
REQUIRED. THE USE OF A PROPERLY SIZED
GAS VENT OR LINER WILL PREVENT
DETERIORATION OF THE CHIMNEY DUE TO
THE EXCESSIVE CONDENSATION WHICH
RESULTS ON OVERSIZED SYSTEMS.
SINGLE-WALL METAL PIPE
Single-wall metal pipe must be of galvanized
sheet or other approved non-combustible
corrosion resistant material, with minimum
thickness per Table 1.8.7, from the National Fuel
Gas Code. Single-wall metal pipe should be
insulated to prevent excessive heat in the boiler
room and to avoid ignition and spillage problems
as well as corrosion from excessive
condensation.
MASONRY, METAL AND FACTORY BUILT
CHIMNEYS
WARNING
UNDER NO CIRCUMSTANCES SHOULD THE
FLUE PIPE BE CONNECTED TO THE
CHIMNEY OF AN OPEN FIREPLACE.
Installation of factory built vents and chimneys
must comply with the vent listing, with the vent
manufacturer's instructions and with adherence to
the codes and clearances as outlined herein.
Masonry or metal chimneys must be built and
TABLE 1.8.7A
TABLE 1.8.7B
WATER BOILER & STEAM BOILERS TO 50 PSIG
(STEAM BOILERS OVER 50 PSIG)
Diameter of
Connector, Inches
Minimum Thickness,
Inch (Gauge)
Diameter of
Connector, Inches
Minimum Thickness,
Inch (Gauge)
6 to 10
10 to 12
12 to 16
16 +
0.023 (24)
0.029 (22)
0.034 (20)
0.056 (16)
14 and less
14 to 16
16 to 18
18 +
0.053 (16)
0.067 (14)
0.093 (12)
0.123 (10)
Download from Www.Somanuals.com. All Manuals Search And Download.
1.8.5 VENT CONNECTORS (HORIZONTAL RUNS)
CONSTRUCTION
Supports should usually be overhead hangers, of
Vent connectors may be of any of the acceptable
constructions listed in this manual.
load bearing capacity appropriate for the weight
involved.
AVOID UNNECESSARY BENDS
LOCATION
The vent connector must be installed so as to
avoid turns or other construction features which
create excessive resistance to flow of flue gases.
When the vent connector used for an appliance
having a draft hood must be located in or pass
through a crawl space or other area difficult to
access or which may be cold, that portion of the
vent connector must be of listed double wall Type
B gas vent material, or of material having
equivalent insulation qualities. Single wall metal
pipe used as a vent connector must not pass
through any floor or ceiling.
JOINTS
Vent connectors must be firmly attached to draft
diverter outlets or boiler flue collars by sheet metal
screws or other approved means. Vent connectors
of Type B vent material must be assembled in
accordance with the vent manufacturer's
instructions. Joints between sections of connector
piping must be fastened using sheet metal screws
or other approved means.
CHIMNEY CONNECTION
In entering a passageway in a masonry or metal
chimney, the vent connector must be installed
above the extreme bottom to avoid stoppage.
Means must be employed which will prevent the
vent connector from protruding so far as to restrict
the space between its end and the opposite wall of
the chimney. A thimble or slip joint may be used to
facilitate removal of the vent connector. The vent
connector must be firmly attached to or inserted
into the thimble or slip joint to prevent the vent
connector from falling out.
SLOPE OR VENT CONNECTOR
The vent connector must be installed without any
dips or sags and must slope upward at least 1/4
inch per foot.
LENGTH OF VENT CONNECTOR
The vent connector must be as short as possible
and the boiler as close as practical to the chimney
or vent.
The horizontal run of an uninsulated vent
connector to a natural draft chimney or vent
servicing a single appliance must not be more than
75% of the height of the chimney or vent above
the vent connector.
The horizontal run of an insulated vent connector
to a natural draft chimney or vent servicing a single
appliance must not exceed 100% of the height of
the chimney or vent above the vent connector.
DAMPERS
Manually operated dampers must not be placed in
the vent connector. This does not exclude the use
of fixed baffles, locking quadrant dampers which
are welded in a fixed position, or automatic vent
dampers (when properly installed and interlocked
with the boiler gas controls).
USE OF THIMBLES
Vent connectors made of single wall metal pipe
must not pass through any combustible wall
unless they are guarded at the point of passage by
ventilated metal thimbles 6" larger in diameter than
the vent connector. This may be done only on
water boilers and steam boilers rated for operation
at no higher than 50 psig.
SUPPORT OF VENT CONNECTOR
The vent connector must be supported in
accordance with the vent manufacturer's
instructions and listing and with all applicable
codes. Support should also be independent of the
boiler or the draft diverter (when used). The vent
connector must be supported for the design and
weight of the material employed to maintain
clearances, prevent physical damage and
separation of joints, and to prevent sagging of the
vent connector.
SINGLE WALL METAL VENT PIPE USED TO
VENT STEAM BOILERS OPERATING OVER 50
PSIG MUST NOT PASS THROUGH WALLS OR
PARTITIONS
CONSTRUCTED
OF
COMBUSTIBLE MATERIAL.
Download from Www.Somanuals.com. All Manuals Search And Download.
1.8.6 CHIMNEY & VENT CONSTRUCTION (VERTICAL SECTION)
INSTALLATION
SYSTEMS
OF
FACTORY
BUILT
Alternatively, a non-ventilating thimble not less
than 18" above and 6" below the roof (with the
annular space open at the bottom and closed at
the top) may be used.
Listed gas vents and factory built chimneys must
be installed in accordance with their listings and
the manufacturer's instructions. Vents and
venting systems passing through roofs must
extend though the roof flashing, roof thimble or
roof jack.
INSPECTIONS OF CHIMNEYS
Before connection of a vent connector to a
chimney, the chimney passageway must be
examined to ascertain that it is clear and free of
obstructions. Cleanouts must be constructed
such that they will remain tightly closed when not
in use. Tee fittings used as cleanouts or
condensate drains must have tight fitting caps to
prevent entrance of air into the chimney at such
points. When an existing masonry chimney is
unlined and local experience indicates that vent
gas condensate may be a problem, an approved
liner or another vent must be installed. When
inspection reveals that an existing chimney is not
safe for the intended application, it must be rebuilt
to conform to nationally recognized standards,
relined with a suitable liner, or replaced with a gas
vent or chimney suitable for the appliances to be
attached.
INSTALLATION OF MASONRY OR METAL
CHIMNEYS
Masonry or metal chimneys must be built in
accordance with nationally recognized building
codes and standards.
INSTALLATION OF SINGLE WALL GAS VENTS
Single wall metal pipe may be used only for runs
directly from the space in which the appliance is
located through the roof or exterior wall to the
outer air. A pipe passing through a roof must
extend without interruption through the roof
flashing, roof jack or thimble. Single wall metal
pipe must not originate in any unoccupied attic or
concealed space. Additionally, it must not pass
through any attic, inside wall, concealed space or
through any floor. Minimum clearance must be
maintained between the single wall metal pipe
and any combustible surface as outlined in Table
1.8.9.
SUPPORT OF CHIMNEYS AND VENTS
All portions of chimneys must be adequately
supported for the design and weight of the
materials employed. Listed factory built chimneys
must be supported and spaced in accordance
with their listings and the chimney or gas vent
manufacturer's recommendations.
When a single wall metal pipe passes through an
exterior wall constructed of combustible material,
it must be guarded at the point of passage by a
ventilated thimble as described under "Use of
Thimbles" in Section 1.8.8 of this manual.
THE GAS VENT OR CHIMNEY MUST BE
SUPPORTED INDEPENDENTLY OF THE
BOILER TOP OR DRAFT DIVERTER.
MINIMUM REQUIRED DISTANCE FROM COMBUSTIBLE MATERIAL
EQUIPMENT TYPE
Listed Vent
not permitted
not permitted
Single Wall Metal Pipe
Factory Built Chimney
as listed
Water and 15 psig Steam Boilers
All Steam Boilers over 15 psig
18"
36"
as listed
Download from Www.Somanuals.com. All Manuals Search And Download.
1.8.7 MARKING OF GAS VENTS
In those localities where solid and liquid fuels are
used extensively, gas vents must be plainly and
permanently identified by a label reading:
"This gas vent is for appliances which
burn gas only. Do not connect to
incinerators or solid or liquid fuel burning
appliances."
The authority having jurisdiction must determine
whether their area constitutes such a locality.
This label must be attached to the wall or ceiling
at a point near where the gas vent connector
enters the wall, ceiling or chimney.
1.8.8 VENTING MULTIPLE APPLIANCES ON A COMMON VENT
COMMON GAS VENT
PRESSURIZED
CONNECTORS
DO NOT CONNECT THE FLUE OF AN
APPLIANCE VENTED BY NATURAL DRAFT TO
A VENT SYSTEM WHICH OPERATES UNDER
A POSITIVE PRESSURE.
VENTS
OR
VENT
When two or more openings (for vent connectors)
are provided in a chimney or gas vent, the
opening should be at different levels. They should
never be opposite one another.
When two vent connectors enter the same gas
vent or chimney, the smallest of the two should
enter at the highest position possible.
SOLID FUEL APPLIANCE VENTS
Gas appliances must not be vented to a vent or a
chimney which serves a solid fuel burning
appliance.
1.8.9 VENT AND CHIMNEY TERMINATIONS
HEIGHT ABOVE ROOF OR OBSTACLE
WATER BOILERS AND LOW PRESSURE
STEAM BOILERS: No less than 3 feet above the
roof and no less than 2 feet above any parapet or
obstacle closer than 10 feet from the vent outlet.
CLEARANCE FROM PUBLIC WALKWAYS
The vent exit of a mechanical draft system must
be at least 7 feet above grade when located next
to public walkways.
HIGH PRESSURE (OVER 15 PSIG) STEAM
BOILERS: No less than 10 feet higher than any
portion of any building within a distance of 25 feet
from the vent.
PROTECTION OF BUILDING MATERIALS
FROM
POSSIBLE
CORROSION
OR
DISCOLORATION FROM FLUE PRODUCTS
The products of combustion from gas or oil
contain potentially corrosive gases and high
temperatures. For this reason, the chimney or
vent exit must be designed to prevent exposure
of the building materials to the flue products.
Failure to do so may result in deterioration or
discoloration of building materials.
MINIMUM HEIGHT ABOVE DRAFT CONTROL
Chimneys and gas vents must extend at least 5
feet above the highest connected barometric draft
control or any appliance flue outlet.
CLEARANCE FROM AIR INLETS
The vent or chimney must terminate no less than
3 feet above any forced air inlet within a distance
of 10 feet. It must terminate no less than 1 foot
above, or 4 feet below, or 4 feet horizontally from,
any door, window or gravity air inlet into a
building.
VENT SUPPORT
The gas vent or chimney must be securely
positioned and supported. Guy wires or other
reliable means must be used to prevent
movement of the vent.
Download from Www.Somanuals.com. All Manuals Search And Download.
PROTECTION AGAINST BLOCKAGE OR
OBSTRUCTION
The chimney or vent exit design must prevent any
possibility of blockage by snow or any other
obstruction.
Listed gas vents must be terminated with a listed
cap, approved for use with the particular gas
vent.
Listed vent caps or roof assemblies must have a
rated venting capacity no less than the vent.
VENTILATING
SYSTEMS
HOODS
AND
EXHAUST
Single wall vents must terminate in an approved
cap which does not obstruct the exit. The
preferred type of cap for natural draft vented
atmospheric boilers is the Briedert Cap. This is
because of the protection this cap provides
against wind-generated downdrafts.
Ventilating hoods or exhaust systems may be
used to vent atmospheric gas appliances. When
these are used, however, such mechanical
exhaust devices must be electrically interlocked
with all appliances on the vent system. The circuit
must prevent the operation of any appliance on
the system if the hood or exhaust system is not in
operation.
Where there is no concern of high winds or
turbulence at the vent exit, a low resistance
conical cap may be used. See Fig. 1.8.12B for
typical dimensions. The diameter of this type cap
should be twice the vent diameter. The cap must
be securely positioned on the vent such as to
provide a clearance of one vent diameter above
the vent exit.
STACK CAPS
EVERY GAS VENT MUST BE SUPPLIED WITH
AN APPROVED VENT CAP WHICH WILL
PREVENT THE ENTRANCE OF RAIN OR
OTHER PRECIPITATION INTO THE VENT.
FAILURE TO PROVIDE SUCH A CAP MAY
CAUSE SEVERE BOILER CORROSION,
COMBUSTION PROBLEMS, OR BOTH.
FIG. 1.8.12B: LOW RESISTANCE VENT CAP
1.8.10 AUTOMATIC VENT DAMPERS
ONE APPLIANCE ONLY
INSTALLATION
An automatic vent must be installed such that it
serves only one appliance vent - that to which it is
properly interlocked.
The damper installation must comply with
Appendix I, J, or K of the National Fuel Gas
Code, NFPA 54. The installation must also
comply with the automatic vent damper listing,
the damper manufacturer's instructions and all
applicable local or state building codes.
LISTING REQUIREMENTS
Automatic vent dampers, if used, must be of a
listed type.
Download from Www.Somanuals.com. All Manuals Search And Download.
AUTOMATIC VENT DAMPERS MUST BE
INSTALLED ONLY BY QUALIFIED SERVICE
TECHNICIANS. FAILURE TO PROPERLY
INSTALL A VENT DAMPER WILL CREATE A
SEVERE HAZARD.
PERFORMANCE TEST
The automatic vent damper must be tested after
installation to assure its proper and safe
operation.
AUTOMATIC VENT DAMPERS MUST BE IN
THE OPEN POSITION AT ANY TIME THE
APPLIANCE MAIN GAS VALVE IS ENERGIZED.
1.8.14 SIZING OF CHIMNEY AND VENT
IMPORTANT
the gas input. Consult the factory or the local
Bryan Representative for the proper parts. For
the purpose of vent system sizing, assume full
input and determine sizing as if at sea level. The
derate factor of 4% per 1000 feet above sea
level accounts for the increased volume per
Btu/hr of flue products at high altitude.
The flue system calculations which follow in
Section 1.8.15 are applicable to double-wall or
insulated single wall breechings (vent connectors)
and stacks (vents). Do not apply these
calculations to uninsulated vent systems.
HIGH ALTITUDES
At altitudes of 2000 feet and higher, atmospheric
boilers must be derated. The amount of derate
required by the National Fuel Gas Code is 4% per
1000 feet above sea level. Boilers which are
shipped from the factory prepared for these
altitudes have the gas orifices properly sized for
this derate. The altitude and gas Btu content for
which the boilers have been constructed is listed
on the Equipment List/Submittal Data in the boiler
manual. The boilers will also be provided with a
label indicating that they have been prepared for
high altitude. If a boiler is to be installed at an
altitude other than that for which it was factory
built, orifices must be replaced to properly adjust
INDUCED DRAFT FANS
Occasionally, the characteristics of an installation
are such that a natural draft vent system will not
suffice. In such cases, induced draft may be
used. The vent system is then sized with an
available "pumping" action equal to the total
theoretical draft plus the static pressure capability
of the induced draft fan. This will result in a
smaller diameter vent than for a natural draft
system. Sizing of induced draft fans should be
done using the recommendations of the fan
manufacturer and the ASHRAE Handbook.
FIG. 1.8.14: SUGGESTED APPLIANCE VENTING PROCEDURE
MULTIPLE APPLIANCE INSTALLATIONS
individual venting is not possible, boilers may be
vented to a common breeching (vent connector).
See Fig. 1.8.14B for recommended design of
such a system. Note that connections of
individual boiler or appliance vents into the
common breeching should
Bryan recommends that boilers and other gas
appliances be individually vented when possible.
See figure 1.8.14A. Individual venting provides
better draft control and fuel efficiency, and is less
likely to cause condensation in the system. When
Download from Www.Somanuals.com. All Manuals Search And Download.
be done with 45
elbows and not by
provide a relatively constant flue gas velocity
through the vent system. Using a constant
diameter breeching will often result in poor draft
at the outermost appliances.
"bullheading" directly into the vent connector at
90 angles. "Bullhead" connections generally
cause excessive turbulence and poor draft
conditions. On vent connectors serving multiple
appliances, the diameter of the piping should be
increased at each appliance's entrance so as to
1.8.12 QUICK SELECTION FOR VENT SIZING CHARTS
GENERAL
must be checked against such local
These charts were generated using the
procedure described in Chapter 26 of the
ASHRAE Equipment Handbook (1979). The
results are consistent with those of the National
Fuel Gas Code.
requirements.
RECTANGULAR VENTS
Vent systems may be rectangular as well as
circular. Table 1.8.15F has been provided to give
the circular equivalent of rectangular duct. These
equivalent values account for the higher pressure
drop per cross section area for rectangular ducts.
The sizing herein is applicable to vent systems
utilizing double wall listed Type B vent as well as
single wall insulated vent with insulation
equivalent to double wall insulating value.
STEP 1: EQUIVALENT INPUT
CONTROL FACTOR
-
DRAFT
Determine the boiler (system) Draft Control
This sizing procedure is not applicable to vent
systems utilizing single wall uninsulated vents or
vent connectors.
Factor, F1, from Table 1.8.15A.
Determine the boiler (or total system) input in
MBH. This is done by dividing the boiler (or total
system) input in Btu/hr by 1000.
The sizing information given herein is intended as
a general recommendation only. Vent sizing and
installation must comply with local codes.
Multiply the total input times factor F1.
The responsibility for assurance of such
compliance is that of the system designer and/or
the system installer. All sizing and installation
The equivalent input, I, (without altitude
correction) is then:
I = MBH x F1
eq. 15A
TABLE 1.8.15A: DRAFT CONTROL FACTOR F1
Multiply factor time input in MBH
Boiler Type
Factor, F1
1.000
Atmospheric with Draft Hood
Atmospheric with Barometric
Forced Draft Gas or Oil
0.741
0.602
STEP 2: EQUIVALENT INPUT - ALTITUDE
FACTOR
Determine the boiler (system) Altitude Correction
Factor, F2, from Table 1.8.15B.
The altitude correction factor, F2 for atmospheric
boilers is equal to 1, because their inputs are
already derated for altitude.
The equivalent input, I, with corrections for
altitude is:
Multiply the boiler (or total system) input times
factors, F2 and F1 for the equivalent input.
I = MBH x F1 x F2
eq. 15B
Download from Www.Somanuals.com. All Manuals Search And Download.
Table 1.8.15B ALTITUDE CORRECTION FACTOR, F2
(Multiple factor times sea level input, MBH)
Altitude (ft)
Factor, F2
Altitude (ft)
Factor, F2
0 to 1999
2000
2500
3000
3500
4000
4500
5000
5500
1.00
1.075
1.096
1.116
1.136
1.157
1.180
1.202
1.25
6000
6500
7000
7500
8000
8500
9000
10000
1.247
1.272
1.296
1.322
1.346
1.373
1.399
1.453
STEP 3: SELECT TRIAL DIAMETER
STEP 4: CALCULATE SYSTEM K-FACTOR
The system "k-factor" accounts for the pressure
drop through fittings and vent piping. It is
calculated by adding up the individual k-factors
for each of the fittings plus the k-factor for the
vent pipe(s).
Determine the NET STACK HEIGHT for the vent.
(The net stack height is the vertical distance from
the top of the atmospheric boiler draft control to
the top of the stack. On forced draft boilers it is
the distance from the boiler flue connection to the
top of the stack.)
From Table 1.8.15D find the k-factors for each of
the elbows, tee fittings, draft regulators, etc. in the
system. Then calculate the vent piping k-factor
from the formula:
Find the vent of TRIAL STACK DIAMETER. Enter
Table 1.8.15C at the Net Stack Height column
equal to the system net stack height. Then
proceed down the column to the input which is
just larger than the equivalent to an input which is
just larger than the Equivalent Input of the
system. Read the Trial Stack Diameter in the left
hand column.
kpiping = 0.4 x L/D
eq. 15C
L = total length of piping in feet
D = diameter of piping in inches
Add all the k-factors together to determine the
total system k-factor:
ktotal = kpiping + kfittings
eq. 15D
NOTE: This is only a trial diameter. Proceed to
Step 4 to calculate the system k-factor to
determine the actual stack diameter required.
NOTE: On multiple appliance systems, multiply
the k-factor times 1.5. This is required only on
atmospheric boiler vent systems, not on forced
draft systems.
Table 1.8.15D: Vent Fitting k-Factors
Vertical Draft Hood
Barometric Draft Control
1.50
0.50
Low Resistance Cap
Round Elbow, 90 deg F
Round Elbow, 45 deg F
0.75
0.30
Converging Exit
Cone
(D1/D2)4 - 1
(D1 is larger than D2)
Tee or 90 degF Breeching
Y Breeching
1.25
0.75
Tapered Reducer
1 - (D2/D1)4
(D1 is larger than D2)
Download from Www.Somanuals.com. All Manuals Search And Download.
STEP 5: CORRECT EQUIVALENT INPUT FOR
SYSTEM K-FACTOR
Multiply the equivalent input calculated in Step 2
times factor F3 from Table 1.8.15E. This step will
yield a new equivalent input, I:
The capacities listed in Table 1.8.15C are based
on a system k-factor equal to 7.5. For any other
k-factor, the vent capacity must be adjusted. This
is accomplished by adjusting the equivalent input
for the system using a k-factor correction factor,
designated F3.
I = MBH x F1 x F2 x F3 eq. 15E
Using this adjusted equivalent input, check the
stack diameter by following Steps 2 thru 3 again.
If the stack diameter remains the same, the sizing
is complete. If not, redo Steps 4 thru 5 etc. until
Refer to Table 1.8.15E for the equivalent input
correction factor which applies to the k-factor
calculated in Step 4. This factor is designated as
F3.
an
acceptable
result
is
achieved.
Table 1.8.15E: K-Factor Equivalent Input Correction Factor F3
K- Factor F3 K- Factor F3 K- Factor F3
K- Factor F3
K- Factor F3
1.00 0.37
1.50 0.45
2.00 0.52
2.50 0.58
3.00 0.63
3.50 0.68
4.00 0.73
4.50 0.77
5.00 0.82
5.50
6.00
6.50
7.00
7.50
8.00
8.50
9.00
9.50
0.86
0.89
0.93
0.97
1.00
1.03
1.06
1.10
1.13
10.00
10.50
11.00
11.50
12.00
12.50
13.00
13.50
14.00
1.15
1.18
1.21
1.24
1.26
1.29
1.32
1.34
1.37
14.50
15.00
15.50
16.00
16.50
17.0
17.50
18.00
18.50
1.39
1.41
1.44
1.46
1.48
1.51
1.53
1.55
1.57
19.00
19.50
20.00
20.50
21.00
21.50
22.00
22.50
23.00
1.59
1.61
1.63
1.65
1.67
1.69
1.71
1.73
1.75
Download from Www.Somanuals.com. All Manuals Search And Download.
Stack
Diam.
(in.)
Table 1.8.15C: Approximate Stack Capacities (MBH)
(Based on Atmospheric Boiler with Draft Hood)
5
7
10
12
150
15
20
25
30
35
40
280
45
50
320
60
70
80
90
100
450
125
510
150
550
200
640
6
100
120
140
170
200
220
250
270
300
350
380
400
430
7
130
160
190
210
240
270
310
340
360
390
410
430
480
510
550
580
620
690
760
870
8
180
210
250
280
310
360
400
440
480
510
540
570
620
670
720
760
810
900
990
1140
1450
1790
2580
3510
4590
5810
7170
8680
10330
12120
14060
16140
18360
20730
23240
41320
52290
64560
92970
9
220
270
320
350
390
450
510
560
600
640
680
720
790
850
910
970
1020
1260
1820
2480
3240
4100
5070
6130
7300
8570
9940
11410
12980
14650
16430
29210
36970
45650
65740
1140
1410
2040
2770
3620
4590
5670
6860
8160
9580
11110
12760
14510
16390
18370
32660
41340
51040
73500
1250
1550
2330
3040
3970
5030
6210
7510
8940
10490
12170
13970
15900
17950
20120
35780
45290
55910
80510
10
12
14
16
18
20
22
24
26
28
30
32
34
36
48
54
60
72
280
330
400
430
490
560
630
690
750
800
850
890
980
1060
1520
2070
2710
3430
4240
5130
6110
7170
8310
9540
10860
12260
13750
24400
30930
38190
55000
1130
1630
2220
2900
3670
4530
5480
6530
7660
8890
10200
11610
13110
14700
26130
33070
40830
58800
1200
1730
2350
3070
3890
4810
5820
6920
8130
9430
10820
12310
13900
15590
27710
35080
43310
62360
400
480
570
630
700
810
910
1000
1360
1770
2250
2770
3360
4000
4690
5440
6250
7110
8020
9000
1080
1470
1920
2430
3000
3630
4320
5070
5880
6750
7680
8670
9720
1150
1570
2050
2590
3200
3880
4610
5420
6280
7210
8210
9270
10390
1220
1660
2170
2750
3400
4110
4900
5750
6660
7650
8710
9830
1290
1750
2290
2900
3580
4340
5160
6060
7030
8070
9180
10360
1410
1920
2510
3180
3920
4750
5650
6640
7700
8840
10050
11350
12730
22630
28640
35360
50920
550
650
780
860
960
1110
1450
1830
2260
2740
3260
3830
4440
5100
5800
6550
7350
1240
1620
2050
2530
3060
3650
4280
4970
5700
6490
7320
8210
720
850
1020
1290
1600
1940
2300
2710
3140
3600
4100
4630
5190
9230
1120
1420
1750
2120
2530
2960
3440
3950
4490
5070
5670
10120
1250
1590
1960
2370
2820
3320
3850
4420
5020
5670
6360
910
1080
1340
1620
1930
2260
2630
3010
3430
3870
4340
7730
1130
1370
1630
1910
2220
2550
2900
3270
3670
6530
8260
10200
14700
11020 11620
19600 20660
24800 26140
30620 32280
44100 46480
11310 13060 14600 16000 17280 18470
14320 16530 18480 20250 21870 23380
17680 20410 22820 25000 27000 28870
25460 29400 32870 36000 38890 41570
9780 11690 12810
12070 14430 15810
17390 20780 22770
NOTE: The above vent input capacities in MBH (thousands of Btu/hr) are sea level ratings for double wall or insulated vents allowing for a system K factor of
7.5. Apply the correction factors for altitude, other k-factors and boiler draft control correction factors.
Download from Www.Somanuals.com. All Manuals Search And Download.
Table 1.8.15F: CIRCULAR EQUIVALENTS OF RECTANGULAR BREECHINGS & STACKS
WIDTH
HEIGHT (INCHES)
(INCHES)
6
7
8
8
9
8
8
9
10 12 14 16
10 10
10 11 11 12
18
11
13
15
16
17
19
20
21
22
23
24
24
25
27
29
31
33
34
20
11
13
15
17
18
20
21
22
23
24
25
26
27
29
31
33
35
37
22
12
14
16
18
19
20
23
24
25
26
27
28
31
33
35
37
39
39
24
12
15
17
18
20
21
23
24
25
26
27
28
29
32
34
37
39
40
26
13
15
17
19
21
22
24
25
26
27
28
29
31
33
36
38
40
42
28
13
16
18
20
21
23
24
26
27
28
29
31
32
35
37
40
42
44
30
14
16
18
20
22
24
25
27
28
29
31
32
33
36
39
41
44
46
36
15
15
17
20
22
24
26
27
29
31
32
35
36
39
42
45
48
50
42
16
19
21
23
26
28
29
31
33
34
36
37
39
42
46
49
52
55
48
17
20
22
25
27
29
31
33
35
37
38
40
41
45
49
52
56
59
54
17
21
23
26
29
31
33
35
37
39
40
42
44
48
52
56
59
62
60
18
21
24
27
30
32
34
37
39
40
42
44
46
50
55
59
62
66
6
8
9
8
10
12
14
16
18
20
22
24
26
28
30
36
42
48
54
60
10 11 12 13 14
11 12 13 14 15
10 11 13 14 15 16
10 12 14 15 16 17
11 13 15 16 17 19
11 13 15 17 18 20
12 14 16 18 19 20
12 15 17 18 20 21
13 15 17 19 21 22
13 16 18 20 21 23
14 16 18 20 22 24
15 17 20 22 24 26
16 19 21 23 26 28
17 20 22 25 27 29
17 21 23 26 29 31
18 21 24 27 30 32
1.8.16 SPECIAL APPLICATIONS
FLUE GAS ECONOMIZERS
HIGH EFFICIENCY APPLIANCES
When applying flue gas economizers, care must
be taken to assure that:
1. Proper draft must be maintained. This requires
that the gas side pressure drop be considered
and that the economizer exchanger must be
designed so as to allow cleaning.
2. The vent system materials must be considered,
regarding resistance from corrosion, which might
result from the lower flue gas temperature.
3. In general, it is recommended that the boiler
manufacturer be consulted when a flue gas
economizer is to be added.
High efficiency appliances require special
consideration in vent design because of the
reduced stack gas temperatures. Under no
circumstances can a condensing type appliance
be vented into the same vent system with other
appliances. The vent system for such appliances
must be provided by or specified specifically by
the manufacturer of the condensing appliance.
High efficiency non-condensing appliances
should
generally be installed only on vent
systems that are resistant to corrosion from flue
gas condensate. This generally requires stainless
steel vent construction.
Download from Www.Somanuals.com. All Manuals Search And Download.
1.9 BURNERS AND GAS TRAIN - FORCED DRAFT BOILERS
GENERAL
Oil supply lines must be sized for the circulation
Refer to separate manual on the forced draft
burner for start-up and adjustment procedures.
Do not attempt to start burner when excess oil
has accumulated, or when the combustion
chamber is full of gas, or if chamber is very hot.
rate of the burner pump. This is referred to as the
suction gear capacity of the pump. If a transfer
pump is used, it must have a pumping capacity
no less than the total suction gear capacity of all
burner pumps on the system. Refer to Burner
Manual for the suction gear capacity of standard
oil pumps. Two-pipe oil systems are
recommended in all cases, although a one-pipe
system might be acceptable on smaller boilers
(under 6 gph). Two-pipe systems tend to have
fewer problems with air entrainment in the oil. Air
in the oil will cause nuisance problems and
delayed ignition.
FUEL CONNECTIONS
Gas supply connections must comply with the
National Fuel Gas Code (NFPA54). Oil supply
connections must comply with NFPA31. Any
additional local or state codes must also be
adhered to.
1.10 PROCEDURES TO BE FOLLOWED BEFORE PLACING BOILER IN
OPERATION
1.10.1 HYDROSTATIC TEST OF BOILERS AND
SYSTEM
although the boiler is hydrostatically tested at the
factory, minor leaks in fittings and at attachments
can develop from shipping vibration or from
installation procedures. It is often necessary to
retighten such fittings after the installation and
after the boiler has been operated for some time.
Replace tube access panels before proceeding to
start boiler.
After completing the boiler and burner installation,
the boiler connections, fittings, attachments and
adjacent piping must be inspected for leaks by
filling the unit with water. The pressure should be
gradually increased to a pressure just below the
setting of boiler safety relief valve(s).
Remove the boiler tube access panels (see
dimensional drawing in this manual). Inspect the
tube to header joints to be certain that all tube
fittings are sealed. This is necessary because,
1.10.2 TEST OF GAS PIPING
Reference gas system test under Section 1.5,
"Gas Connection", in this manual.
Download from Www.Somanuals.com. All Manuals Search And Download.
START-UP AND OPERATION
STEAM BOILERS
WARNING:
IMPROPER SERVICING AND START-UP OF THIS EQUIPMENT MAY CREATE A
POTENTIAL HAZARD TO EQUIPMENT AND TO OPERATORS OR PERSONS IN THE
BUILDING.
SERVICING AND START-UP MUST BE DONE ONLY BY FULLY TRAINED AND
QUALIFIED PERSONNEL.
CAUTION:
BEFORE DISCONNECTING OR OPENING ANY FUEL LINE, OR BEFORE CLEANING OR REPLACING
PARTS OF ANY KIND, TAKE THE FOLLOWING PRECAUTIONS:
Turn OFF the main fuel shutoff valves, including the pilot gas cock if applicable. If the burner is a multiple
fuel type, shut OFF all fuel supplies.
Turn OFF all electrical disconnects to the burner, boiler and any other equipment or systems electrically
interlocked with the burner or boiler.
All cover plates, enclosures, and guards must be in place at all times except during maintenance and
servicing.
2.1 FIRING RATE ADJUSTMENT - ATMOSPHERIC GAS UNITS
2.1.1 The following procedures must be followed
carefully before putting the boiler in operation.
Failure to do so will present severe hazards to
equipment, operating personnel and building
occupants.
which firing rate system is used, see the boiler
Equipment List and Wiring Diagram.
2.1.4 ADJUST BOILER MINIMUM INPUT
After setting the correct Maximum input as
described in the Lighting Instructions, proceed to
adjust the minimum input as outlined below. This
applies only to those boilers which are designed
and equipped for two-stage (High/Low/Off) firing
or Modulation. On those boilers which are
equipped for ON/OFF firing only, no minimum
input adjustment is required. NOTE: the low firing
rate input is adjustable only on boilers equipped
with two-stage or modulating motorized gas
valves (V4055, V9055, or AH4 actuators) or with
motor-operated modulating butterfly gas valves.
The other two-stage firing systems (VR850 or
VR852 combination valves or dual diaphragm
valve type bypass systems) have a non-
adjustable minimum input rate.
2.1.2 ADJUST PILOT BURNER
Carefully follow the Lighting Instructions in the
boiler manual for the proper adjustment of the
pilot burner. This is absolutely essential before
attempting to adjust the main burner.
2.1.3 ADJUST BOILER INPUT(S)
The boiler input must be adjusted for both
maximum and minimum input values which are
listed on the boiler nameplate. First adjust the
maximum input rating using the method
described in Lighting Instructions in the Boiler
Manual. Refer to the following information for the
adjustment of the minimum input. To determine
the adjustment
Download from Www.Somanuals.com. All Manuals Search And Download.
NOTE
2.1.6 MINIMUM INPUT ADJUSTMENT - DUAL
DIAPHRAGM GAS VALVE HIGH/LOW BY-PASS
SYSTEM
THE LOW FIRE ADJUSTMENT SHOULD
RESULT IN A GAS PRESSURE ON THE
BURNER MANIFOLD EQUAL TO 1" WATER
COLUMN FOR NATURAL GAS AND 3" FOR
PROPANE GAS.
The minimum input on this control system is NOT
adjustable. The maximum input must be properly
set as outlined in Lighting Instructions. This
system consists of two V48A (120 volt coil) or two
V88A (24 volts coil) diaphragm gas valves which
are piped in parallel. The minimum input is
controlled by an orifice plug installed in a coupling
in the by-pass piping (low fire valve piping), sized
for approximately 1" w.c. manifold pressure at low
fire natural gas (2" w.c. if propane gas). When the
high fire gas valve is not activated, gas flows only
through the bypass piping. When the high fire gas
valve is activated, gas will flow though both
valves achieving full input.
2.1.5 MINIMUM INPUT ADJUSTMENT
COMBINATION GAS VALVES (VR850 OR
VR852)
The minimum input on these gas valves is NOT
adjustable. The maximum input must be properly
set as outlined in Lighting Instructions. See the
manufacturer's instructions on the VR850 or
VR852 included in the Boiler Manual for further
information.
-
2.2 FIRING RATE ADJUSTMENT - GAS METER READINGS
2.2.1 CHECKING BURNER INPUT
calculated from this timing. The method is
The burner input rate can be checked by taking
readings from the gas meter. Please note
checking the rate with a meter is the only way to
be sure of input. Manifold readings are only an
approximate value and may vary from unit to unit.
described in Lighting Instructions. If the meter is
not calibrated for gas temperature and pressure,
correction factors must be applied to determine
correct rate in SCFH (standard cubic feet per
hour). Consult the National Fuel Gas Code (ANSI
Z223.1, NFPA 54) or the local gas utility for
further information. Refer to Table 2.2A for
correction factors for the gas pressure at the
meter. Refer to Table 2.2B for the gas
temperature correction factors.
In order to obtain accurate data, there must be no
other appliances using gas from the same meter
while the burner input rate is being checked. The
test hand on the meter should be timed for
several revolutions. The input rate in cubic feet
per hour is
Table 2.2A - Pressure Correction
Table 2.2B - Temperature Correction
Gas Pressure at Meter
7" w.c.
Correction Factor
Gas Temp. at Meter
Correction Factor
0.920
1.017
1.034
1.051
1.061
1.136
1.340
40
50
60
70
80
90
F
F
F
F
F
F
14" w.c.
0.902
21" w.c.
0.885
1 psig
0.868
2 psig
0.852
5 psig
0.836
Download from Www.Somanuals.com. All Manuals Search And Download.
2.3 SAFETY SHUT-OFF DEVICES (FLAME SUPERVISION)
2.3.1 FLAME SUPERVISORY SYSTEM
flame loss. In addition to the information given in
The boiler is equipped with a flame supervisory
system, either the Thermocouple type (such as a
combination gas valve or a pilotstat) or electronic
type (such as the RA890, or RM7895). The
purpose of this device is to detect the main or
pilot flame, depending on the type of device, and
control the gas valves accordingly. The device
must be checked for proper operation. See
Lighting Instructions in the Boiler Manual for the
correct procedure. The flame supervisory system
must be tested to assure that it will shut off the
main gas valves in case of a
Lighting Instructions, operating sequence and
troubleshooting information may be found in the
manufacturer's instructions in the Boiler Manual.
2.3.2 AUTOMATIC (ELECTRIC) IGNITION
SYSTEMS
On boilers equipped with automatic electrically
ignited pilots, follow the procedures described in
Lighting Instructions and test the controls for
proper operation.
2.4 LIMIT CIRCUIT CUT-OUT TEST
2.4.1 PROTECTIVE DEVICES
All operating and limit controls and low water
cutoffs must be tested for proper operation.
water feeder combination) or electric probe type
auxiliary control. These water level controls are
intended to sense (and control) the level of the
water in the boiler. They operate to shut off the
boiler if the water level drops below their sensing
level. The low water cut-off and water level
controls must be operationally tested by manually
lowering the boiler water level (by opening the
boiler blowdown valve for probe controls, and by
opening the control blowdown valve for float type
controls). The boiler should cycle off when the
water level drops below the control point of the
low water cut-off. When the water level is
restored, the boiler should cycle back on.
Depress the manual reset button of devices
which require manual reset in order to restore the
boiler to operation. Carefully read the enclosed
literature on the low water cut-off controls,
particularly installaing, operating and servicing.
2.4.2
STEAM
PRESSURE
OPERATING
CONTROL
The steam pressure in the boiler is regulated by
the Boiler Operator. This is a pressure control
which senses the steam pressure and turns the
boiler on and off accordingly. This control must be
operationally tested. Adjust the pressure setting
on the control to a pressure less than the boiler
pressure (as shown on the boiler pressure
gauge). The control should turn the boiler off.
Restore the control setting to normal. The boiler
should cycle on.
2.4.3 HIGH LIMIT CONTROL
At least one additional pressure control is
provided as the high limit control. It is set at a
pressure above the operator to act as a back-up
should the operator fail. The high limit control
must be operationally tested. With the boiler
operating, decrease the pressure setting of the
limit control below the current pressure of the
boiler. The boiler should cycle off. Restore the
high limit control setting to normal (pushing rest
button if it is a manual reset type). The boiler
should now cycle on.
2.4.5 COMBINATION LOW WATER CUT-OFF &
FEEDER
The low water cut-off/feeder supplied with some
boiler serves as a low water cut-off (see above)
and also causes make-up water to be added to
the boiler should the water level drop below its
control point.
This type of control must be operationally tested
as for low water cut-offs and also to assure that
the make-up water is introduced as needed.
Carefully read the enclosed literature on the Low
2.4.4 LOW WATER CUT-OFF(S)
Most boilers are supplied with a float-operated
primary low water cut-off (and pump control or
Download from Www.Somanuals.com. All Manuals Search And Download.
Water Cut-off controls, particularly installing,
operating and servicing.
2.4.7 BOILER FEED SYSTEM
The boiler feed pump must be operationally
tested to assure that it can provide boiler
feedwater at the pressure and in the amount
needed for safe and reliable boiler operation.
2.4.6 OTHER CONTROLS
Additional controls as required for the particular
installation may also be provided. Refer to the
literature on these devices included in the Boiler
Manual. All such devices must be operationally
tested to assure reliable operation of the boiler
and system.
2.4.8 CHEMICAL FEED SYSTEM & SOFTENER
Check the performance of the boiler water
softener and chemical treatment system.
Chemically test the feedwater to be certain it
complies with the recommendations of the
chemical treatment consultant.
2.5 RECOMMENDED DRAFT AND COMBUSTION READINGS
ATMOSPHERIC GAS-FIRED BOILERS
BOILER SERIES
DRAFT AT BOILER CO2 @ HIGH
O2 @
HIGH FIRE
CO
(ppm)
SMOKE
NO.
OUTLET
(i.w.c.)
FIRE
F
CL
K
-0.01 TO -0.04
-0.02 TO -0.04
-0.02 TO -0.06
7.5 TO 8.5 % 5.0 TO 7.5 %
7.5 TO 9.0 % 4.8 TO 7.5 %
8.0 TO 9.5 % 4.0 TO 6.7 %
< 400
< 400
< 400
0
0
0
FORCED DRAFT GAS FIRED BOILERS
BOILER SERIES
DRAFT AT
BOILER
CO2 @
HIGH FIRE
O2 @
HIGH FIRE
CO
(ppm)
SMOKE
NO.
OUTLET (i.w.c.)
D
HED
-0.01 TO -0.04
-0.01 TO -0.04
0.0 TO -0.04
7.5 TO 9.5 %
7.5 TO 9.5 %
4.0 TO 7.5 %
4.0 TO 7.5 %
< 400
< 400
< 400
< 400
< 400
< 400
0
0
0
0
0
0
CL
8.5 TO 10.0 % 3.2 TO 5.0 %
8.5 TO 10.0 % 3.2 TO 5.0 %
9.0 TO 10.0 % 3.2 TO 5.0 %
9.0 TO 10.0 % 3.2 TO 5.0 %
HECL
RV & RW
AB
0.0 TO -0.06
+0.50 TO -0.10
+0.25 TO -0.06
Download from Www.Somanuals.com. All Manuals Search And Download.
FORCED DRAFT OIL FIRED BOILERS
BOILER SERIES
DRAFT AT
BOILER
CO2 @
HIGH FIRE
O2 @
HIGH FIRE
CO
(ppm)
SMOKE
NO.
OUTLET (i.w.c.)
D
CL
-0.01 TO -0.04
0.0 TO -0.04
10.0 TO 12.0 % 4.0 TO 7.2 %
10.0 TO 12.0 % 4.0 TO 7.2 %
11.5 TO 12.5 % 3.7 TO 5.0 %
11.5 TO 12.5 % 3.7 TO 5.0 %
< 400
< 400
< 400
< 400
0
0
0
0
RV & RW
AB
+0.50 TO -0.10
+0.25 TO -0.06
NOTE: THE VALUES FOR CO2 AND O2 ARE SHOWN FOR HIGH FIRE ONLY. THE VALUES FOR LOW
FIRE OR MID RANGE WILL GENERALLY BE LOWER, PARTICULARLY FOR ATMOSPHERIC GAS-
FIRED BOILERS. DRAFT SHOULD BE MEASURED APPROXIMATELY 24" FROM TOP OF BOILER,
BEFORE ANY DRAFT CONTROL.
2.5.1 DRAFT ADJUSTMENT - ATMOSPHERIC
GAS BOILERS
ARE MADE TO ASSURE ADEQUATE DRAFT
THROUGH THE VENTING SYSTEM.
2.5.2 DRAFT ADJUSTMENT -FORCED DRAFT
BOILERS
Draft adjustments are generally not necessary on
forced draft boilers. The draft must be measured
as part of the start-up procedure. The measured
draft at the boiler flue should fall within the
recommended range specified in the appropriate
table.
Refer to Section 1.8.6 for the adjustment method
for barometric dampers. Adjust the damper so as
to yield a draft which results in values of CO2 and
CO within the allowable limits listed above in the
appropriate table.
Draft adjustments are generally not required for
boilers equipped with draft diverters. The diverter
must
be
installed
without
modification.
Combustion readings are required, however, to
assure that the boiler operation is both safe and
efficient.
On some installations the draft may be excessive
due to a high chimney. In these cases, the draft
should be adjusted within the recommended
range specified in the above appropriate table.
This may be done using a barometric damper, a
restrictor, or a locking quadrant damper. Such
devices must be installed and adjusted by a
qualified technician.
Draft measurement should preferably be made
with an inclined tube manometer. If a draft gauge
is not available, check to be sure the flue gases
are being carried up the venting system by
passing a lighted taper or match around the edge
of the draft hood relief opening (or barometric). If
the venting system is operating correctly, the
match flame will be drawn toward the draft hood
relief opening. Otherwise the products of
combustion will tend to push the flame and
extinguish it.
2.5.3
COMBUSTION
ADJUSTMENTS
-
FORCED DRAFT
Refer to the separate burner manual for the
procedures for burner adjustments. The burner
must be adjusted for smooth lightoff. Combustion
parameters should be within the range specified
in the above appropriate table. In no case should
the level of CO be allowed to exceed the limit
given, and the smoke spot reading must also not
exceed the value shown.
CAUTION
IF THE PRODUCTS OF COMBUSTION ARE
BEING EMITTED INTO THE ROOM (VENTING
SYSTEM NOT OPERATING CORRECTLY),
THE BOILER MUST NOT BE OPERATED
UNTIL PROPER ADJUSTMENTS OR REPAIRS
Download from Www.Somanuals.com. All Manuals Search And Download.
2.6 OPERATING INSTRUCTIONS
2.6.1 FAMILIARIZATION WITH MANUAL(S)
The user of the boiler must familiarize himself
with this manual and the burner manual for forced
draft boilers to be sure he is prepared to operate
and maintain the boiler properly.
The operating instructions should be kept in the
pocket in the boiler for F Series boilers, or
adjacent to the boiler for all others.
READ THE MANUAL BEFORE ATTEMPTING A
START UP.
2.7 MAINTENANCE SCHEDULE
2.7.1 POSTING SCHEDULE
Post a maintenance schedule in accordance with
the recommendations in this manual. A copy of a
typical schedule is included in this manual.
Section 3
Download from Www.Somanuals.com. All Manuals Search And Download.
CARE AND MAINTENANCE
STEAM BOILERS
CAUTION:
•
•
The boiler area should be kept free of combustible materials, gasoline and other flammable liquids.
The boiler and venting system must be kept free of obstructions of the air louvers and draft hood
relief openings.
•
•
The following procedures must be conducted as outlined to assure safe operation of the boiler.
All cover plates, enclosures, and guards must be in place at all times except during maintenance
and servicing.
3.1 REQUIRED PRECAUTIONS DURING TEMPORARY USE
GENERAL
1. Knowledge of burner/boiler operation.
A boiler is often utilized in new construction to
assist in curing of building components or to
provide temporary heat for the construction crew
or for other purposes during the time the building
is under construction. If precautions are not taken
during this time to protect the boiler, a great deal
of damage can occur before the ultimate owner
takes over the building.
2. Possession and understanding of boiler/burner
operating instruction manual.
3. Assurance that the boiler is fed with only
treated water at all times and that chemical
treatment and blowdown procedures are always
followed.
It is the mutual responsibility of the installing
contractor and the boiler owner to consider the
effect of temporary usage on the boiler warranty.
The following should be observed so as to assure
the longevity of the boiler.
4. Notification to the manufacturer (or
manufacturer's agent) to provide start-up services
if the boiler was purchased with start-up by a
factory representative.
5. Adherence to all of the start-up procedures
noted in the boiler/burner manual.
OPERATOR SKILLS/RESPONSIBILITIES
During the temporary use period, a single
individual must be assigned responsibility for the
care and operation of the boiler. This person's
responsibility must include, but not be limited to,
the following:
6. Considerations of warranty should the boiler be
used for temporary heat without adherence to the
recommended start-up and operating procedures
outlined in the instruction manuals.
3.2 CLEANING THE BOILER AND SYSTEM - NEW SYSTEMS
BOIL OUT PROCEDURE
In combination with system contamination,
The internal surfaces of a newly installed boiler
will have oil, grease or other protective coatings
used in manufacturing. Such coatings must be
removed since these coatings lower the heat
transfer rate and could lead to overheating of a
tube and reduce operating efficiency. Before
boiling out procedures may begin, the burner
must be ready for firing. The operator must be
familiar with the procedure outlined in the
boiler/burner operating instruction manuals.
bacteria may cause objectionable odors,
sometimes resembling natural gas. It is important
to keep these fumes from air intakes which would
distribute them throughout the building. On steam
humidification systems this is especially critical.
Consult your local water treatment chemist for
further information.
Download from Www.Somanuals.com. All Manuals Search And Download.
CAUTION
6. Fill the boiler with clean softened water until the
water level reaches the upper header. Then add
the cleaning solution into the upper header. Add
more clean water until the boiler is completely
filled. The water used for this initial fill should be
at room temperature, and must be softened as
noted.
The boil out procedure outlined must be
performed by, or under the direct supervision of,
a qualified technician. The chemicals used
present a hazard of burns and physical injury if
mishandled. Always use suitable face mask,
goggles, protective gloves and garments when
handling caustic chemicals. Do not permit the
chemical to come into contact with skin or
clothing. Always follow the safety precautions on
the container's label. Add chemicals slowly and in
small amounts to prevent excessive heat and
agitation. Do not add water to acid. Do not add
water to dry chemical. This will cause splattering
and/or explosion and severe risk of personal
injury.
7. After filling, fire the boiler intermittently (at low
fire) at a frequency as necessary to hold the
boiler solution at boiling point temperature. DO
NOT PRODUCE STEAM PRESSURE. Boil the
water, supervised at all times, for at least five
hours.
8. After the five hour boil out, begin to add a small
amount of fresh softened water so as to create a
slight overflow of the overflow pipe. This will carry
out impurities which have accumulated at the
water surface. Continue to apply heat and
overflow until the water emitted from the overflow
pipe clears. Then shut off burner.
Boiling out under pressure is not recommended.
If boil out under pressure is required, competent
assistance must be provided.
Your water consultant or water treatment
company will be able to recommend a cleaning or
boil out procedure. In the event that such service
is unavailable or as yet not selected, the following
may be used.
9. Let the boiler cool to 120 F or less. Then drain
the boiler. Use caution that the water is
discharged with safety.
10. Remove the inspection/cleanout openings in
the boiler upper and lower headers and wash the
waterside surfaces thoroughly using high
pressure water stream.
1. The boil out of the boiler and system is neither
difficult nor expensive. The chemicals needed for
cleaning are readily available. Trisodium
phosphate, and sodium hydroxide (lye) are the
most commonly used chemicals. Use only one
type of solution in the system. The amount of
chemical required will vary according to
conditions, but an amount of one pound of
chemical per fifty gallons of water is suggested.
11.
Inspect the boiler's internal (waterside)
surfaces thoroughly after the procedure. If the
surfaces are not clean, repeat the boil out.
12. After boil out, close all openings. Install relief
valves, gauge glasses and other components as
necessary. Completely fill the boiler with fresh,
softened, ambient temperature water. Fire the
boiler at low fire until water temperature of at least
180 F is reached. This will drive off dissolved
gases.
2. Before introducing the solution into the boiler,
an overflow pipe should be attached to the top of
the boiler and routed to a safe point of discharge.
3. Remove all safety valves to ensure that none
of the solution will come into contact with the
valve seats. Use care in removing and reinstalling
valves.
13. The boiler is now ready to operate.
4. All valves in the piping to and from the system
must be closed to prevent the chemical solution
from getting into the system.
IMPORTANT
If boiler is not to be operated within 24 hours, a
lay-up procedure is required. Refer to instruction
for lay-up.
5. Gauge glasses must be protected from contact
with the boil out chemicals.
Download from Www.Somanuals.com. All Manuals Search And Download.
3.3 SYSTEM CLEAN OUT
Many boilers have been ruined with system
contaminants such as pipe dope, cutting oil,
metal shavings or chips and other debris which
are left in the piping. If these contaminants are
not removed, they will end up in the boiler.
During this system clean out, the boiler make-up
water must be properly softened and treated. At
the conclusion of the system clean out, the
condensate must be reconnected.
For old or existing steam systems, the installation
process may have jarred debris loose. Following
the boil out of the new boiler, the condensate
should be wasted until it is within proper
guidelines. Check all steam trap strainers to
assure their cleanliness. Refer to the succeeding
section on replacement boiler installations.
SYSTEM CLEANING PROCEDURE
For steam systems, the boiler will need to be
connected to the header utilizing steam to purge
the piping and thus push the debris out of the
system. However, at this time all condensate
must be wasted until it runs clear and water
analysis of the condensate indicates that it is free
of contaminants. Steam trap strainers must be
periodically opened and cleaned of any debris
which accumulates.
3.4 REPLACEMENT BOILER INSTALLATIONS:
PROTECTION AGAINST CORROSION & SEDIMENT
BOILER MUST CONTROL FEED WATER
The water feed to the boiler must be controlled by
the boiler-mounted water level control. It is
unacceptable to use gravity return or to let the
water feed be controlled by a condensate/
receiver/ condensate pump system. The water
feed to the boiler must be controlled:
the entire system. A chemical treatment company
should be consulted for the proper means of this
chemical cleaning.
Replace any piping considered to be deteriorated
beyond safe or cleanable condition. Flush the
system clean, being certain to isolate the boiler.
by a feed pump control which is mounted on
the boiler. This control is to activate the feed
pump on a boiler feed system. It will be
necessary to supply such a system if not already
installed. - OR -
by an automatic water feeder mounted on the
boiler. This is used only on systems requiring
100% make-up, such as humidification, steam
process, etc.
DO NOT FLUSH THE SYSTEM THROUGH THE
BOILER
NOTE: For some old systems, there is a
reluctance to clean the piping because of the
possibility of leaks occurring in badly corroded
lines. Should the customer refuse cleaning, it is
necessary to install filtration equipment. Install
either a fibrous filter or a centrifugal filter in the
boiler return piping. This will collect and remove
sediment from the system. A booster pump may
have to be installed as well to overcome the
additional pressure drop introduced in the line by
the filter. When filling the system, provide
chemical treatment as outlined in Section 3.5.
NOTE
It is not recommended to provide the make-up for
a closed steam heating system to the boiler by
means of a water feeder. It is preferred that
system make-up be connected to the condensate
return tank of a boiler feed system.
A boiler feed system may be used in conjunction
with an existing condensate receiver system by
allowing the receiver system to pump condensate
into the boiler feed system tank.
CAUTION
Failure to properly clean the system or to install
mechanical sediment removal equipment can
result in tube blockage and severe corrosion plus
damage to pumps, controls, and air removal
device.
CLEAN OR REPLACE ALL SYSTEM PIPING
AND HEATING UNITS
Arrange for chemical and mechanical cleaning of
Download from Www.Somanuals.com. All Manuals Search And Download.
3.5 BOILER WATER TREATMENT
PURPOSE OF WATER TREATMENT
WATER SOFTENER
Water treatment is required for satisfactory
operation of the boiler. It must be devised to
prevent depositing of scale and to prevent
corrosion from acids, oxygen and other such
harmful elements that may be in the water supply.
A qualified water treatment chemist should be
consulted and the water systematically treated.
It is highly recommended that a zeolite water
softener be used for all make-up to the boiler. It is
intended that this be used in addition to the
chemical treatment of the boiler. Water softening
removes calcium and magnesium, the primary
causes of hard boiler scale.
CONTINUOUS MONITORING REQUIRED
Water treatment should be checked and
maintained whenever the boiler is operating. The
boiler operator should be sure that the boiler is
not operating for long periods without proper
water treatment. Water treatment may vary from
season to season or over a period of time.
Therefore, the water treatment procedure should
be checked not less than four times a year, and
possibly more frequently as the local water
conditions may indicate.
OBJECTIVES
The basic objectives of water treatment are:
1. Prevent the accumulation of scale and
deposits in the boiler.
2. Remove dissolved gases from the
water.
3. Protect the boiler against corrosion.
4. Maintain the highest possible boiler
fuel efficiency.
5. Decrease the amount of boiler down
time from cleaning.
3.6 EXTERNAL "FIRE-SIDE" CLEANING
PURPOSE
If the buildup of soot is appreciable, the flue gas
venting system must be thoroughly inspected
internally as well, and cleaned as necessary.
Carbon (soot) is an insulator and is corrosive.
The heating surface of a boiler must be kept free
from soot accumulation to keep the boiler
operating at its highest efficiency and to avoid
damage from corrosion.
IMPORTANT
If either soot or condensation is apparent, a boiler
service technician should be consulted. The
presence of soot indicates poor combustion and
possibly hazardous boiler operation. Failure to do
so may result in fire, explosion potential, or
asphyxiation. A combustion test and burner
adjustments should be undertaken at once.
SOOT REMOVAL
If the yearly inspection of the boiler tube surfaces
reveals a build-up of either soot or rust (usually
due to condensation), the tubes should be
thoroughly brushed. (Tube cleaning brushes are
available from Bryan Steam) To inspect and, if
necessary, clean the tube surfaces and flue
collector, first remove the tube access panels.
Examine the exterior of the tubes for evidence of
soot or rust. Using a flashlight, carefully look
between the tubes. There should be an
unobstructed opening between all tubes, and the
top surfaces of the tube must be free from soot
accumulation. Also inspect the interior of the flue
collector. Brush or vacuum the soot from all
surfaces. Be sure to cover atmospheric burners
with a protective cover during cleaning to prevent
soot from falling into them.
Rust on the tubes indicates that boiler-operating
temperatures are too low. The set point of the
boiler operating control must be no less than
130 F for natural gas or propane firing, and
170 F for oil fired boilers. Boilers equipped with
outdoor reset control must also follow these
limits.
Download from Www.Somanuals.com. All Manuals Search And Download.
3.7 SUGGESTED MAINTENANCE SCHEDULE
DAILY
MONTHLY
1. Make visual inspection of gauges, monitors, and
indicators and record readings in boiler log.
1. Make visual inspection of linkage and proper
operation of flue, vent, stack, or outlet dampers. Check
draft as specified in Section 2 of this manual.
2. Make visual check of instrument and equipment
settings against factory recommended specifications.
2. Check float low water cutoff as described above.
3. Check operation of float type low water cutoffs to
ensure control is functioning. The lower piping
connections of float type level controls should have a
suitable blowdown valve piped into a proper drain. This
valve should be opened periodically to allow any sludge
accumulated in the control to be flushed out. On closed
loop water heating systems this should not be often
required. Consult manufacturer's instructions.
3. For those units equipped with a power burner, check
low draft, fan, air pressure and damper position
interlocks as specified in burner manual.
4. Check high and low gas pressure interlocks. Refer to
manufacturers instructions for correct procedure.
5. Check high and low oil pressure interlocks. Refer to
manufacturers instructions for correct procedure.
WEEKLY
1. On units equipped with firing rate control, verify that it
is functioning correctly by adjusting control and
observing if input changes accordingly.
ANNUALLY
1. Perform leakage tests on pilot and main gas or main
oil fuel valves as specified in manufacturers instructions.
2. Make visual inspection of igniter and pilot flame. For
an atmospheric unit, confirm pilot flame is as shown in
this manual (Section 1.9) and that the main burners light
off correctly (smoothly) and that the flame is clean and
normal. For units with a power burner, check pilot flame
signal strength as specified in burner manual.
2. Check operating control, high limit, low fire start
control, and low water cutoff as specified in
manufacturers instructions.
3. For units equipped with power burners, check air
atomizing interlock, fuel valve interlock switch, purge
switch, burner position interlock, and fuel changeover
control, as specified in burner manual.
3. Check pilot and main fuel valves for correct operation.
Open limit switch - make audible and visual check -
check valve position indicators and check fuel meters, if
supplied.
4. The boiler should be checked at least yearly by the
local gas utility company. Particular attention should be
paid to the pilot burner safety devices. The pilot burner
should be checked to ensure that prompt ignition of all
burners occurs as the gas valve opens. Refer to Section
1.9.
4. Confirm boiler area is free of combustible materials
and that there is nothing obstructing air openings, draft
hood relief openings, etc.
5. Check combustion safety controls for flame failure
and flame signal strength as specified in manufacturer's
instructions located at the back of this manual for
atmospheric units or in the burner manual for units
equipped with a power burner.
5. The flue gas passages and the exterior surfaces of
the boiler tubes should be inspected at least annually.
Any accumulation of soot or debris should be thoroughly
cleaned out.
6. If the yearly inspection of the boiler tube surfaces
reveals a build-up of soot (carbon) or rust, the tubes
surfaces should be thoroughly brushed. Failure to do so
may result in fire or asphyxiation hazards.
6. Check all limit controls as specified in manufacturer's
manual.
7. Check float low water cutoff as described above.
7. The boiler pressure vessel and piping should be
checked annually.
8. Check combustion safety control for pilot turndown
and refractory hold-in as specified in manufacturer's
instructions.
Download from Www.Somanuals.com. All Manuals Search And Download.
3.8 FLOAT-ACTUATED WATER LEVEL CONTROLS
Inspect float type water level controls for proper
operation. Visually inspect sight glasses for
evidence of scale forming residues. Refer to
section 3.9 for gauge glass maintenance.
On humidification or process systems, the
blowdown schedule should be based on
recommendation from a water treatment and
maintenance program specifically designed for
the boiler.
On closed steam heating systems, the float low
water cutoff should be blown down by means of
At the annual inspection, all float type level
controls should be disassembled, cleaned and
inspected thoroughly. When re-installed these
controls must be given an operational test.
opening
a
blowdown valve on the lower
connection of the cutoff once per day.
3.9 WATER GAUGE GLASSES
INSTALLATION
INSPECTION
Check with the maintenance supervisor and
engineering for the proper glass to be used.
Compare the box and the glass label or marking
to ascertain that the gauge glass ratings or
temperature and pressure are suitable for use on
the boiler. Use new gaskets when replacing
glass. The gaskets used should be the same type
as those originally supplied with the boiler. Make
certain that the gauge glass valves are properly
aligned.
To examine for scratches, shine a bright
concentrated light at about a 45 angle. Anything
that glistens brightly should be inspected closely.
Any scratch which glistens and will catch a
fingernail, or crescent-shaped or star-shaped
mark is cause for replacement. This is because
scratches, corrosion, chips and surface damage
weaken the glass. If inner surface appears cloudy
or roughened, and will not respond to cleaning
procedures, this is evidence of chemical attack. If
severe, this is cause for replacement.
All bolts and nuts must be free running and well
lubricated, preferably with
a
graphite type
REPLACEMENT OF GLASS
lubricant. Washers under nuts and bolt heads are
desirable. DO NOT tighten while equipment is in
operation.
Any glass that has been removed from its
mounting in process boilers, regardless of the
reason for removal, should be discarded and
replaced with a new glass and gaskets. Used
glasses may contain hidden damage and
represent a safety hazard.
MAINTENANCE
Inspect the gauge glass regularly for any signs of
clouding or scratching. In new processes, the
gauge glass should be inspected daily until the
need for replacement becomes apparent. This
will help establish the routine inspection cycle.
Be sure that the replacement glass is suitable for
service conditions.
Protective shields to keep cold air, water, or
falling objects from glass must be replaced.
The gauge glass should be blown down daily so
as to remove accumulated sediment from the
valves.
Download from Www.Somanuals.com. All Manuals Search And Download.
Download from Www.Somanuals.com. All Manuals Search And Download.
4.0 IDLE BOILER CARE AND LAY-UP
GENERAL
(when used) should be kept to a minimum so the
reduction of solids is achieved by the increased
manual blowdown.
Corrosion damage to boilers is often the result of
improper lay-up during non-operating periods.
Substantial damage can occur in only a few days
in proper precautions are not taken. This damage
is irreversible and will reduce boiler reliability,
increase maintenance costs and eventually
shorten the useful life of the boiler tubes.
WASHDOWN
As the boiler cannot be washed immediately, the
heat in the boiler may cause baking of residual
sludge. The boiler should not be drained until
cooled enough to prevent this. However, never
leave the boiler filled with water for any extended
period of time without taking measures to prevent
corrosion.
Idle boilers are vulnerable to attack when air
contacts untreated wet metal surfaces. To prevent
corrosion, the boiler metal must be protected by
either keeping the surfaces completely dry or
excluding air from the boiler. Air exclusion is
accomplished either by keeping the boiler
completely full of water (short term lay-up) or filling
the boiler with nitrogen gas (long-term lay-up).
The nitrogen gas prevents air infiltration and does
not react with the metal.
LAY-UP CONSIDERATIONS
There are two basic methods of steam boiler lay-
up: Wet lay up or Dry lay-up. The choice of which
method should be used depends on:
The possibility that the boiler may need to be
placed in operation on short notice.
Disposal of lay-up solutions
In addition to the corrosion damage that occurs,
the metal particles that are released will form an
insulating scale on the tubes when the boiler is
returned to service. These corrosion products will
accumulate on critical heat transfer areas of the
boiler, increasing the potential for localized
corrosion and over heating.
Freezing potential
Wet Lay-up is recommended for relatively short
outages, such as seasonal lay-up. This method
has the advantage of allowing the boiler to be
brought on line with short notice. But it can pose
problems if there is any likelihood of freezing.
PRE-OPERATIONAL CLEANING AND LAY-UP
Proper lay-up techniques must be used on an idle
boiler even if it has never been in operation.
Before pre-operational lay-up, the boiler must be
chemically cleaned as outlined in Section 3.2 of
this manual. This is required, as noted in this
section, to remove preservatives, oil and grease
from the tube surfaces. Follow the short term or
long term lay-up procedure as appropriate.
Dry Lay-up is recommended for longer periods of
boiler shut-down or storage. But it is practical only
if boiler can be drained hot (120 F to 170 F) or if
external drying can be provided.
WET LAY-UP OF STEAM BOILERS - SHORT
TERM
In the wet lay-up procedure, the boiler is to be
filled with chemically treated water and sealed to
prevent air in-leakage. Nitrogen gas under slight
pressure can also be used to displace air and
protect the boiler surfaces from corrosion. The
following steps should be taken for wet lay-up of a
boiler:
TAKING BOILERS OFF LINE
In operation, boiler water contains suspended
solids which are held in suspension due to water
circulation and the action of treatment chemicals.
Unless care is exercised when draining the boiler,
these suspended solids settle on the tube
surfaces and will air dry to an adherent deposit,
sometimes requiring chemical cleaning to remove.
In addition, these deposits may be misleading
regarding the effectiveness of the chemical
treatment program.
1a. Procedure for operational boiler:
At least thirty minutes before the boiler comes off
line, add the following chemicals:
Sodium Sulfite - 0.5 lbs. per 100 gallons water
Polymeric Sludge Dispersant - 0.1 lbs. per 100
gallons water
Caustic Soda - 0.3 lbs. per 100 gallons water
PRE-SHUTDOWN PRECAUTIONS
For a period of three to seven days prior to
shutdown, manual blowdown frequency should be
increased. During this period, the lower
conductivity limit should be below 3500 micro-
mohs per centimeter. The feed of internal
treatment must be increased to maintain a specific
residual concentration. Continuous blowdown
1b. Procedure for idle boiler:
If the boiler has never been on line or has been
out of service for cleaning - Select the highest
quality water available to fill the boiler. Steam
condensate, softened water, filtered fresh water,
and boiler feedwater are generally acceptable for
Download from Www.Somanuals.com. All Manuals Search And Download.
lay-up. Raw city water is not recommended and
should not be used.
chemical. Then repeat Step. 2. Pay attention to
the maintenance of the valves being used to
isolate the boiler to prevent leakage and resultant
dilution of the lay-up solution.
Prepare the chemical solution described in (1a) in
a separate tank. Adhere to the safety precautions
described in Section 3.2 of this manual. Add the
concentrated lay-up solution to the boiler during
the time it is being filled.
ALTERNATE METHOD
An alternate wet lay-up method is to pipe clean
continuous blowdown water from a properly
treated boiler into any convenient bottom
connection on the idle boiler, allowing the water to
flow through the boiler and out the top (through
any convenient top opening) to the sewer. This
method will insure a continuous, complete fill with
warm, properly treated water. It also prevents in-
leakage of air by keeping the boiler slightly
pressurized. It may also provide enough heat to
keep the fireside of the boiler dry and possibly
produce adequate freeze protection.
After the boiler is filled and the lay-up solution has
been added, the boiler is to be operated for thirty
minutes at low fire to circulate and mix the
chemicals.
2. After filling, the boiler must be closed or
blanked tightly. The power supply to the boiler
must be cut off. Vent all air from the top of the
boiler to allow complete fill with the required
solution. Nitrogen gas at 5 psig may be introduced
though a suitable opening to prevent air in-
leakage during the lay-up period. An alternative to
the nitrogen gas (see safety precautions under dry
lay-up) is to install a 55 gallon drum or auxiliary
vessel as shown in Figure 3.11A. This is to be
fitted with a cover and filled with properly treated
water. This vessel or drum should be connected
to an available opening in the top of the vessel. Its
purpose is to create a hydrostatic head and to
allow a ready visual check of water level loss or
in-leakage during the lay-up period.
DRY LAY-UP OF STEAM BOILERS - LONG
TERM
The dry lay-up method recommended requires
that the boiler be drained, dried as completely as
is possible, all opening and valves closed.
Nitrogen gas at 5 psig is introduced to the boiler to
pressurize it and prevent air in-leakage. The
success of the procedure depends on the
thorough drying of the boiler metal surfaces after
draining and the exclusion of air during the lay-up.
CAUTION
The use of nitrogen for blanketing is
recommended in both the wet and dry lay-up
procedures. Even though nitrogen in dilute
quantities is non-toxic, it will not support life.
Precautions must be taken before entering
equipment filled with nitrogen for inspections or
any other purposes. These precautions shall be
as follows:
disconnection of nitrogen supply line
complete purging and venting of the equipment
with fresh air
testing oxygen levels inside before any attempt
to enter
Figure 3.11A: WET LAY-UP STATIC HEAD
DRUM
all confined entry guidelines applicable to site
must be followed
3. During lay-up, test the boiler weekly to assure
the proper levels of sulfite and alkalinity. To do
this, take a sample of the boiler water from the
surface blowdown line or other high point. The
test results should be:
Sodium Sulfite 200 ppm minimum
Phenolphthalein Alkalinity (as CaCO3)
400 ppm minimum
Appropriate caution signs shall be posted around
the equipment to alert personal that nitrogen
blanketing is in use. A boiler laid up dry must be
tagged with information that the unit is not to be
operated until the boiler is properly refilled.
If the tests indicate chemical concentration has
decreased, chemical may be introduced to the
boiler by putting it in the drum shown in Fig.
3.11A. Then lower the boiler water level to
introduced it into the boiler. Then operate the
boiler at low fire to circulate the water and mix the
1. Drain the boiler before the steam pressure falls
to zero. Then pressurize with 5 psig nitrogen gas
through a suitable top opening during draining.
The nitrogen pressure is to be maintained through
draining and subsequent storage.
Download from Www.Somanuals.com. All Manuals Search And Download.
An alternate method is to completely dry a clean
boil (by blowing hot dry air though the boiler) and
then purge the air from the boiler and pressurize
with 5 psig nitrogen. Be aware that all metal
surfaces which are not completely dry are
vulnerable to corrosion, particularly if oxygen is
present.
1. If the boiler was pressurized with nitrogen,
disconnect the nitrogen supply source and vent
the boiler.
2. Using the blowdown valve, drain the boiler
partially and make up with feedwater so as to
dilute the chemical residuals to operating
concentration levels.
2. If a boiler has been down for repairs and is to
be laid up, it should be operated to pressurize with
steam and then drained and pressurized with
nitrogen as in step 1.
3. After the boiler water concentrations and the
water level are returned to proper operating
conditions, the boiler can be started in the normal
manner.
3. All connections must be blanked or tightly
closed.
After Dry Lay-Up
To start an idle boiler after dry lay-up, use the
following procedure:
Note: Operating boilers must be removed from
service to minimize adherence of boiler water
suspended solids on boiler metal surfaces. Refer
to previous instructions for boiler washdown.
1. Disconnect the nitrogen supply source and vent
the boiler in a safe manner - external to the
building and away from air intakes. Then
thoroughly purge the boiler of nitrogen with dry air.
RETURNING IDLE BOILER TO SERVICE
After wet lay-up
To start an idle boiler after wet lay-up, use the
following procedure:
2. The boiler was to have been cleaned before the
lay up procedure. So it is necessary only to fill the
boiler with properly treated water. Then proceed
with start-up.
Download from Www.Somanuals.com. All Manuals Search And Download.
|